By John Lee.
Iraq's Ministry of Transport has announced that the Nasiriyah International Airport project has reached over 56% completion, with significant progress following the resolution of obstacles faced by the Chinese contractor.
Key Data:
- Project: Nasiriyah International Airport
- Completion Rate: 56%
- Total Workers: 450
- Machinery in Use: Over 120 units
- Main Buildings:
- Passenger terminal (20,000 sqm, 2 floors: departures and arrivals)
- VIP lounge (2,000 sqm)
- Control tower (42 meters tall)
- Air navigation staff housing
- Runway:
- Length: 3,400 meters
- Load capacity: PCM 87
- Taxiway length: 3,400 meters
- Airport Capacity:
- Initial: 750,000 passengers annually
- Phase two (after 10 years): More than 2,500,000 passengers annually
- Aircraft Gates: 3
- Aircraft Parking Capacity: More than 8 planes
- Additional Facilities:
- Fuel station
- Water desalination station
- Power station
- Civil defense center
- Standards Compliance: Civil Aviation Authority, ICAO
(Source: Ministry of Transport)