Akri Bijeel Oil Block Declared 'Commercial'

Bijell field:

  • Bijell Extended Well Test ("EWT") surface facility construction and commissioning was finished. Total gross capacity of the EWT facility is 10,000 boepd in phase-1, while storage tanks have 30,000 boe capacity. Under current technical conditions, it is subservient to deviate the well to exclude or minimize the water inflow and increase the oil productivity.Bijell-1B sidetrack drilling, testing and completion to be finished in Q1 2014.
  • Drilling of Bijell-7 appraisal well was finished at total depth of 5,050 m at end of June, drilled 10 km to the south-south-east of the Bijell‑1 discovery well. Jurassic reservoir section found tight during the vertical drilling. It was followed by a highly deviated sidetrack which confirmed oil saturation, however, the reservoir was poorly fractured and was not capable of flowing naturally even after stimulation.
  • Bijell-2 well was spud on 13 March 2013, currently drilling the upper Jurassic section. Planned TD is 5330m, will be tested in Q1 2014.
  • Further steps aiming at the completion of the appraisal program including the drilling and testing of Bijell-4 & -6 by Q3 2014 in case of both wells. A full coverage 3D seismic will be available for the Bijell area in November 2013.
  • Early oil production could be resumed from Bijell-1B in Q1 2014, subsequently adding B-2, B-4 and B-6 on stream by the Q3 2014. Expected EPF plateau of 10,000 bbl of oil could be achieved by the end 2014.

(Source: GKP)